West Pennant Hills Culvert
Published: Sep 2019Project: Culvert
Location: West Pennant Hills, NSW
Profiles: 155mm & 275mm
Project Details: 11m length (5 cells)
Advantages of Dincel design
All materials moved around and on-site without crane (original design required 250tonne crane)
Lead time reduced from 18 weeks to immediate availability
Project not affected by rain
Benefits to Contractor
Cheaper, quicker and easier construction
Allowed second stage subdivision work to proceed much earlier
Improved cash flow